CLICK HERE TO DOWNLOAD PPT ON DC Supply System
DC Supply System Presentation Transcript
1.DC Supply System
2.Presentation outline
Duties
DC Loads
DC system
Types of Batteries
Duties
DC Loads
DC system
Types of Batteries
3.DC SYSTEM IS DESIGNED
TO SUPPLY HIGH STANDARD OF RELIABLE & SECURE DC POWER
TO PROVIDE CONTINUOUS & QUALITY POWER AS AND WHEN REQUIRED
UNDER NORMAL & ABNORMAL OPERATING CONDITIONS
ULTIMATE & FINAL DC BACK-UP POWER TO EQUIPMENT AND DC DRIVES WHEN TOTAL AC SUPPLY FAILS
HENCE THEY ARE BATTERY BACKED
TO SUPPLY HIGH STANDARD OF RELIABLE & SECURE DC POWER
TO PROVIDE CONTINUOUS & QUALITY POWER AS AND WHEN REQUIRED
UNDER NORMAL & ABNORMAL OPERATING CONDITIONS
ULTIMATE & FINAL DC BACK-UP POWER TO EQUIPMENT AND DC DRIVES WHEN TOTAL AC SUPPLY FAILS
HENCE THEY ARE BATTERY BACKED
4.DUTIES
TO SUPPLY EQUIPMENT WHICH REQUIRES DC DURING NORMAL CONDITIONS
TO SUPPLY STANDBY EQUIPMENT/DC DRIVES
TO SUPPLY STARTERS OF VARIOUS EQUIPMENT
TO SUPPLY EQUIPMENT WHEN AC SUPPLIES HAVE BEEN LOST
TO SUPPLY EQUIPMENT WHICH REQUIRES DC DURING NORMAL CONDITIONS
TO SUPPLY STANDBY EQUIPMENT/DC DRIVES
TO SUPPLY STARTERS OF VARIOUS EQUIPMENT
TO SUPPLY EQUIPMENT WHEN AC SUPPLIES HAVE BEEN LOST
5.Types of Power Supplies In a Power Plant
11KV/3.3KV/415V AC Power Supply
415V AC Emergency Supply(DG)
DC Power Supply
UPS Supply
11KV/3.3KV/415V AC Power Supply
415V AC Emergency Supply(DG)
DC Power Supply
UPS Supply
6.DC Power Supply
Various Critical Drives
Emergency DC Lighting
Switchgear Control Supply for closing & tripping
Control, Protection And Interlocks
Indication, Annunciation & Alarm System
Public Address System
DAS And Communication System
Various Critical Drives
Emergency DC Lighting
Switchgear Control Supply for closing & tripping
Control, Protection And Interlocks
Indication, Annunciation & Alarm System
Public Address System
DAS And Communication System
7.DC Supplies……………Why?
Emergency Lube Oil Pump
Emergency Jacking Oil Pump
Emergency Scanner Air Fan
Emergency Seal Oil Pump
Breaker/Unit Protections
Emergency Lighting
Emergency Lube Oil Pump
Emergency Jacking Oil Pump
Emergency Scanner Air Fan
Emergency Seal Oil Pump
Breaker/Unit Protections
Emergency Lighting
8.The Ultimate Backup
In case of unit tripping / grid failure, either station changeover takes place / DG would start.
Normally, grid supply would be restored in minimum possible time and DG would shut down.
In case of DG failure, the DC backup comes in to service to facilitate safe shut down.
In case of unit tripping / grid failure, either station changeover takes place / DG would start.
Normally, grid supply would be restored in minimum possible time and DG would shut down.
In case of DG failure, the DC backup comes in to service to facilitate safe shut down.
9.Selection of voltage -DC POWER SUPPLY
In power plant D.C. pumps, lighting require comparatively high voltage due to their high power requirement. Hence as a standard these applications are designed with 220V level.
It is desirable to have comparatively lower voltage- 24V/48V/110V for control/indications/annunciation due to safety reasons. However to avoid multiplicity of DC supplies (particularly we require two control supplies), we have adopted uniform 220V DC voltage for plant electrical systems for switchgear control, protection and interlock operation.
In power plant D.C. pumps, lighting require comparatively high voltage due to their high power requirement. Hence as a standard these applications are designed with 220V level.
It is desirable to have comparatively lower voltage- 24V/48V/110V for control/indications/annunciation due to safety reasons. However to avoid multiplicity of DC supplies (particularly we require two control supplies), we have adopted uniform 220V DC voltage for plant electrical systems for switchgear control, protection and interlock operation.
10.DC POWER SUPPLY SCHEME
Earlier concept;
1X100% battery bank along with its chargers for each unit with inter-unit interconnection through high capacity DC bus bar.
In view of large size of above DC loads of each unit and the large unit pitch it is necessary to provide a separate DC system (battery +chargers) to enhance the plant’s overall reliability.
2) Present concept;
In view of the reasons explained above 2x100% capacity DC system is provided for each unit and switchyard separately.
Minor DC loads of offsite areas in the plant i.e. WTP, Ash handling are fed from plant DC system as it is now restricted to limited area switchgear rooms
Earlier concept;
1X100% battery bank along with its chargers for each unit with inter-unit interconnection through high capacity DC bus bar.
In view of large size of above DC loads of each unit and the large unit pitch it is necessary to provide a separate DC system (battery +chargers) to enhance the plant’s overall reliability.
2) Present concept;
In view of the reasons explained above 2x100% capacity DC system is provided for each unit and switchyard separately.
Minor DC loads of offsite areas in the plant i.e. WTP, Ash handling are fed from plant DC system as it is now restricted to limited area switchgear rooms
11.DC System
Battery
Battery Charger
Battery
Battery Charger
12.DC SYSTEM
BATTERY CHARGERS [TWO/THREE]
BATTERY BANKS [ONE/TWO]
DC DISTRIBUTION BOARDS [ONE/TWO]
DC FUSE BOARDS
CHARGER TROUBLE, DC EARTH FAULT AND DC VOLTAGE ABNORMAL ALARMS IN UCB
BATTERY CHARGERS [TWO/THREE]
BATTERY BANKS [ONE/TWO]
DC DISTRIBUTION BOARDS [ONE/TWO]
DC FUSE BOARDS
CHARGER TROUBLE, DC EARTH FAULT AND DC VOLTAGE ABNORMAL ALARMS IN UCB
13.220 V Supplies
14.Battery Capacity
Expressed in ampere hour(AH)
Duration of discharge-10 hr for Plante/5 hr for Ni-Cd
End cell voltage-1.85 volt for Lead acid plante/1.0 volt for Ni-Cd
Ambient temperature-27 deg cent.
Electrolyte specific gravity-1.2+-.005 lead acid plante cells
Expressed in ampere hour(AH)
Duration of discharge-10 hr for Plante/5 hr for Ni-Cd
End cell voltage-1.85 volt for Lead acid plante/1.0 volt for Ni-Cd
Ambient temperature-27 deg cent.
Electrolyte specific gravity-1.2+-.005 lead acid plante cells
15.SELECTION OF BATTERY TYPE IN POWER PLANT
Power plant batteries standby duty require high discharge performance with continuously connected on float mode operation.
Expected Life of lead acid tubular is of the order of 8-10 years so in a power plant life of 25 years minimum two replacement would be required.
Lead acid PLANTE and Ni-Cd (alkaline) have expected life of 15-20 years hence only one replacement would be required in whole plant life.
In addition lead acid plante have much better discharge performance than tubular type for the specified emergency duration.
In view of above plante type lead acid or Ni-Cd high discharge batteries are specified for power plant applications.
Power plant batteries standby duty require high discharge performance with continuously connected on float mode operation.
Expected Life of lead acid tubular is of the order of 8-10 years so in a power plant life of 25 years minimum two replacement would be required.
Lead acid PLANTE and Ni-Cd (alkaline) have expected life of 15-20 years hence only one replacement would be required in whole plant life.
In addition lead acid plante have much better discharge performance than tubular type for the specified emergency duration.
In view of above plante type lead acid or Ni-Cd high discharge batteries are specified for power plant applications.
0 comments